The Scrum master page in My view has two sprint charts. This guide says what each line means, why a chart may count work items instead of points, and what the marked last step means.
Steps
- Open My view as Scrum master or team lead, on the Overview view.
- Find How is the sprint burning down? This is the burndown. Left is what is left each day. An even pace is a straight line from what the sprint began with down to nothing on its last day. Its headline says what is left and how many days are to go.
- Find Is the sprint growing as it goes? This is the burnup. In the sprint is what the sprint holds each day; Done is what is finished. Its headline says how much is done, and how much joined after the sprint began.
- Check the unit. Both charts count in points when at least half of the sprint's work carries story points. Otherwise they count work items.
- If the sprint is more than 3 days past its end, look at the last step. The sprint's own days are kept, and the time since its end is one step to today, marked with the days, such as "+12 days".
Expected result
You can tell whether the sprint is ahead of or behind an even pace, and whether it grew after it began.
Common mistakes
- Reading a gap above the pace line as growth. Growth shows on the burnup, as In the sprint rising.
- Expecting a line on the first day. One day is a single point, not a line.
- Expecting a pace line for a sprint that began empty. There is nothing to compare with, so none is drawn.